News Detail
First Platform Installed
July, 2006

Momentum Engineering successfully completed the installation of the Akkaya Jacket. The installation of the Akkaya Jacket marks the completion of the first phase in this fast-track project. The remaining phases in the project will include the installation of of at least two other jackets and each of the three jackets topside structures. The Akkaya jacket was installed in the Black Sea off the northern coast of Turkey, it was 68m in length and weighed over 400 tons. The next jacket scheduled for installation is the East Ayazli jacket. Its installation is expected to be complete in December of 2006.
|